CALIF MEGA-WIND LIVES AT LAST
Wind farm 'mega-project' underway in Mojave Desert; The Alta Wind Energy Center — with plans for thousands of acres of turbines to generate electricity for 600,000 Southern California homes — officially breaks ground…
Tifffany Hsu, July 27, 2010 (LA Times)
"It's being called the largest wind power project in the country, with plans for thousands of acres of towering turbines in the Mojave Desert foothills generating electricity for 600,000 homes in Southern California…
"The multibillion-dollar Alta Wind Energy Center has had a tortured history, stretching across nearly a decade of ownership changes, opposition from local residents and transmission infrastructure delays…[and] is officially breaking ground in the Tehachapi Pass, a burgeoning hot spot for wind energy about 75 miles north of Los Angeles. When completed, Alta could produce three times as much energy as the country's largest existing wind farm…"
Tehachapi wind (photo by NewEnergyNews - click to enlarge)
"The project will probably be a wind power bellwether, affecting the way renewable energy deals are financed, the development of new electricity storage systems and how governments regulate the industry…The project's developer, New York-based Terra-Gen Power, plans to coax three gigawatts of power from the wind farm over the next eight years. It has led some industry experts to predict that California might have a shot at reclaiming the wind energy crown from competitors such as Texas and Iowa…
"Southern California Edison agreed in 2006 to buy 1,550 megawatts of electricity from Alta over 25 years, one of the heftiest power purchase agreements ever signed. That would be enough energy to serve 275,000 homes and is twice the capacity of the country's largest existing wind farm, a 735-megawatt project in Texas…Terra-Gen is building Alta as a collection of wind farms; it has finished funding and started building the first group of five…290 turbines will be scattered across 9,000 acres, most of which are leased from private landowners."
Transmission is the key to growth. (photo by NewEnergyNews - click to enlarge)
"As early as next year…the turbines could start producing enough power to boost California's wind energy output more than 25% while creating thousands of local jobs…By 2015, another batch of farms, with roughly 300 turbines…is expected to be producing an additional 830 megawatts…[Initially conceived] in the early 2000s…[permitting] took about three years…
"Edison has been making headway on its Tehachapi Renewable Transmission Project, connecting alternative-energy projects such as Alta to electricity-hungry city centers. The utility is trying to meet a statewide goal for investor-owned utilities to use renewable energy for 33% of all power supplied to customers by 2020…Previously tight-fisted investors also are more confident about financing renewable energy projects. Terra-Gen recently secured $1.2 billion in funding for the Alta project…the Alta project seems to be on track…"