NewEnergyNews More: DOI APPROVES GIANT PV PLANT

Every day is Earthday.

Some details about NewEnergyNews and the man behind the curtain: Herman K. Trabish, Agua Dulce, CA., Doctor with my hands, Writer with my head, Student of New Energy and Human Experience with my heart

email: herman@NewEnergyNews.net

-------------------

Your intrepid reporter

-------------------

    A tip of the NewEnergyNews cap to Phillip Garcia for crucial assistance in the design implementation of this site. Thanks, Phillip.

-------------------

Pay a visit to the HARRY BOYKOFF page at Basketball Reference, sponsored by NewEnergyNews and Oil In Their Blood.

  • ---------------
  • Tuesday, August 16, 2011

    DOI APPROVES GIANT PV PLANT

    550 MW Desert Sunlight Solar Farm Receives Approval From Secretary Salazar
    11 August 2011 (Solar Industry)

    "U.S. Department of the Interior (DOI) Secretary Ken Salazar has approved the Desert Sunlight Solar Farm, a 550 MW solar PV project to be built in the California desert east of Palm Springs. The decision authorizes the U.S. Bureau of Land Management (BLM) to offer Desert Sunlight Holdings a right-of-way grant to use these public lands for 30 years…

    "The solar facility will create more than 630 jobs at peak construction and infuse an estimated $336 million into the local economy…"


    click to enlarge

    "Located on approximately 4,100 acres of public lands, the project will be developed and operated by Desert Sunlight Holdings LLC, a subsidiary of First Solar Inc. The facility will use First Solar's thin film technology. An on-site substation and a 230 kV generation tie line will connect the project to the Red Bluff substation, which will convert the power from 230 kV to 500 kV for transmission on Southern California Edison's regional grid.

    "The Desert Sunlight project underwent extensive environmental review and mitigation…The proposed project's total footprint was reduced from 19,000 acres down to 4,144 acres…[and] BLM is requiring that Desert Sunlight provide funding for acquisition and enhancement of more than 7,500 acres of suitable habitat for desert tortoise and other sensitive wildlife species to help mitigate the project's potential impacts…[T]he U.S. Department of Energy granted Desert Sunlight a conditional commitment of a $1.88 billion loan guarantee."